In the context of the judicial review actions taken by a coalition of residents and visitors challenging the construction of a cruise ship terminal and dock and the creation of man-made island offshore using material dredged from the sea in North Bimini in the Bahamas, security costs were...
You are here
Jurisprudence
An environmental non-governmental organization challenged the construction and operation of a cruise passenger destination which included a captive marine mammal facility at Blackbeard’s Cay off the Northern Coast of New Providence.
A multinational company applied for permission to engage in exploratory oil drilling in the Sarstoon Temash National Park. The Environmental Impact Assessment for the proposed project was subject to a public consultation, held by the Department of Environment on 25 October 2012.
On 16 February 2007 Jamaica’s National Works Agency (NWA) submitted applications for the construction and dredging projects in the Palisadoes, an area with significant historical, ecological and cultural value.
An application had been filed by an environmental non-governmental organization to the National Environmental and Planning Agency requesting veterinary reports for the Dolphin Cove facilities in Ocho Rios and Montego Bay.
An appeal was lodged before the Privy Council against the Court of Appeal of Bahamas upholding the approval by the Government of the Bahamas, in principle, of a proposed large-scale development in the north-west part of Great Guana Cay, both on land and in the sea, with far-reaching economic,...
Two public spirited organizations applied for judicial review of the decision of the Environmental Management Authority to grant a certificate of environmental clearance (CEC) for the construction of an Aluminium Smelter plant at Union Village, La Brea.
A funerary services company presented an application for judicial review of the decision of the Minister of Local Government and Environment ordering the cessation of the company’s development of a cemetery until a full Environmental Impact Assessment (EIA) had been conducted.
The Mines and Geology Division failed to grant access to all the information requested by an environmental non-governmental organization for maps and documents regarding commencement and completion dates for partial mined and mined out orebodies and certificate of completion and other documents...
On 6 June 2003, the Environmental Management Authority issued a Certificate of Environmental clearance relative to the establishment of an expansion of liquefied gas producing and operation facilities at Point Fortin.